The Sweetwater Phase 3 Wind Farm was the second of five phases of this wind farm that have been completed near Sweetwater, Texas. Phase 2 included 90 General Electric 1.5 MW wind turbines. The project is developed and owned by DKRW and was built as M. A. Mortenson as the general contractor. TRC Engineer’s Inc. under the management of Sentry Engineering Group, Inc. personnel completed the following scopes of work on a turn-key engineer, procure and construct basis:

  • 34.5 to 138 kV Collection substation
  • 138 kV to 345 kV interconnection substation
  • 10 mile 138 kV transmission line connecting the collection substation to the interconnection substation
  • Underground collection system
  • Overhead collection system