Location: Barstow, TX

 

Line Voltage: 25 kV

 

Line Length: 23 miles

 

Conductor Size: 954 ACSR

 

Project Description: Built 23 miles of 3 phase line. Set all new wood and concrete poles and strung in new wire and underground.  Completed crossings of energized lines, and crossings of interstates and railroads.

Published in Distribution Projects
%PM, %14 %700 %2016 %15:%Mar

Oncor - Kinder Morgan

Location: Snyder, TX

 

Line Voltage: 7.2 kV

 

Line Length: 8 miles

 

Conductor Size: 795 ACSR

 

Project Description: New 3 phase and 3 phase reconductor. Installed multiple air brake switches and regulator bank and 3 phase reclosures. Bored under roadway, pulled in underground and made terminations.

Published in Distribution Projects

Location: Tipton, MO

 

Line Voltage: 7.2 kV

 

Line Length: N/A

 

Conductor Size: N/A

 

Project Description: Single and three phase pole change outs.

Published in Distribution Projects

Location: Lovington, NM

 

Line Voltage: N/A

 

Line Length: Pole Change Outs

 

Conductor Size: N/A

 

Project Description: Replacement of Priority one poles and services.

Published in Distribution Projects

Location: Altus, OK

 

Line Voltage: 7.2 kV

 

Line Length: 190 miles

 

Conductor Size: #2 ACSR and 1/0 ACSR

 

Project Description: Reconduct single phase, B phase and three phase. Changing out poles and replacing wire.

Published in Distribution Projects
%PM, %17 %863 %2015 %19:%Feb

Xplorer - Distribution Project

Location: Lindsey, OK

 

Line Voltage: 25 kV

 

Line Length: 1 mile

 

Conductor Size: 477 ACSR

 

Project Description: Strung 3 phase, set 17 poles, pulled in 500 copper underground wire and terminated at switch gear and on pole.

Published in Distribution Projects

Location: Midland/Odessa, TX

 

Line Voltage: 7.2 kV

 

Line Length: N/A

 

Conductor Size: N/A

 

Project Description: Movement of 3 phase and 1 phase distribution circuits, Construction of new 3 phase distribution circuits. Reconductoring 3 phase to 3 phase some double circuit.

Published in Distribution Projects

Location: Clinton, IA

 

Line Voltage: 7.2 kV

 

Line Length: 8 miles

 

Conductor Size: 3/0 ACSR

 

Project Description: Change out poles and reconduct.

Published in Distribution Projects
%PM, %16 %837 %2014 %19:%Apr

New Braunfels Utility Distribution

Location: New Braunfels, Texas
Line Voltage:
Line Length: 3 miles
Conductor Size:
Scope of Work: Reconductoring, and setting wood and steel poles.

Published in Distribution Projects
%PM, %16 %837 %2014 %19:%Apr

Oncor Distribution - Lufkin

Oncor 2014 System Improvements
Location: Lufkin, Texas
Line Votage: 7.2 kV
Line Length: N/A
Conductor Size: N/A
Scope of Work: Movement of 3 phase and 1 phase distribution circuits, Construction of new 3 phase distribution circuits. Reconductoring 3 phase to 3 phase some double circuit.

Published in Distribution Projects
Page 1 of 3

Electrical Construction

Transmission & Distribution

image

image

Transmission & Distribution
Click here to see our list of recent T&D projects.

Wind Projects

image

image

Wind Projects
Click here to see our list of recent Wind projects.